Astronomical duration of tasks

Duration can be set not only in working units, but also in astronomical units. In this case, the task execution schedule will not be interrupted on weekends and holidays, the task will be performed during non-working hours as well. No calendar changes will affect such a task.

Such estimates should not be abused; they are appropriate only if they are driven by the technological peculiarities of the task.

To estimate the duration in astronomical units, it is enough to prefix the letter designation of the unit with the letter A (in the Russian version of the program) or E (in the English version).

For example:

1ed - one day
5ed - 5 days
1ew - exactly 7 days
1em - exactly 30 days