scheduling

Setting the default time units

By default, duration is entered in working days, work is entered in hours. If you estimate tasks in your project in weeks or months, it may be inconvenient to add the time unit letter designation to the estimation each time.

The default setting is performed in the File - Options window on the Schedule tab. Here you should fill in the fields Duration is entered in:, Work is entered in:, by entering your custom units.

Then click OK.
#ProjectProfessional #ProjectOnlineProfessional #Tasks #Scheduling #TimeUnits